The previous on-site parking facility at the School was inadequate to cater for the staff and visitors. The parking overflowed onto the approach road and created major congestion and safety hazard at busy hours.

With the benefit of Planning Permission and the backing of EDSI funding, Acivico designed and managed the project to create a large School car park to accommodate up to 30-cars. The project was successfully completed in November within 10 weeks.  Also installed are new perimeter fencing and a bicycle rack/shelter.

The finish outcome has positively benefited the School with very good feedback from the staff and local residents.    